ETON CYBERPOD CORINTHIAN
April 22, 2010
View along Ortigas Avenue
 
 
March 23, 2010
View along Ortigas Avenue
 
 
February 17, 2010
View along Ortigas Avenue
 
 
January 6, 2010
View along Ortigas Avenue
 
 
December 22, 2009
View along Ortigas Avenue
 
 
November 13, 2009
View along Ortigas Avenue
 
 
October 29, 2009
View along Ortigas Avenue
 
 
October 14, 2009
View along Ortigas Avenue
 
 
September 17, 2009
View along Ortigas Avenue
 
 
August 26, 2009
View along Ortigas Avenue
View along Ortigas Avenue
 
August 12, 2009
View along Ortigas Avenue
View along Ortigas Avenue
 
July 22, 2009
View along Ortigas Avenue
View along Ortigas Avenue
 
July 2, 2009
View along Ortigas Avenue
View along Ortigas Avenue
 
June 18, 2009
View along Ortigas Avenue
View along Ortigas Avenue
 
June 2, 2009
View along Ortigas Avenue
View along Ortigas Avenue
 
May 19, 2009
View along Ortigas Avenue
View along Ortigas Avenue
 
May 5, 2009

View along Ortigas Avenue

View along Ortigas Avenue

 
April 16, 2009

On-going concreting of 3rd floor level at Building 1

Concreted of 4th floor level at Building 1

 
March 19, 2009

Forms removal of concreted roof deck level for stairs and elevators at Building 1

Plastering of window openings at Building 1

 

Ramp and ground floor level at Building 1 & 2 merging area

On going MEPFS works at Building 2, 2nd floor

 

Concreted 3rd floor level & on-going forms installation for 4th floor level at Building 2

Interior plaster at 2nd floor, Building 2 facing Ortigas Avenue

 

On going masonry works at 3rd floor, Building 2 facing Arcadia Clubhouse

On-going rebar works at roof deck level at Building 2

 

Concreted cistern tank floor at Building 3

On-going forms enclosure of cistern tank at Building 3

 

View of Building 3, concreted 2nd floor level and on going form works for 3rd floor Level

View of Building, concreted 2nd floor level

 

Elevators and Escalator delivery

On-going fabrication of mechanical exhaust ducting

 
February 18, 2009

Bird's Eye View of Building 2

View of Building 3

 

On-going masonry works at 2nd and 3rd Level of Building 1 facing Ortigas Avenue

Reinforcement Bars and Forms installation at Roof deck, Building 1 for Elevator Hooks

 

View of Building 2

Concreted Slab at Building 2

 
January 29, 2009

Roofdeck Level of Building 1 facing EDSA

Panoramic View of Building 1

 

Rebar and Formworks for 2nd Floor Level

Concreted 2nd Floor Level

 

Bird’s eye View of Building 2

Concreted Ground Floor Level and 2nd Floor Level

 

On-going rebar and formworks installation for Basement 1 Level

Retaining Wall Status along Arcadia Entrance

 

Building 3

On-going masonry works

 

On-going masonry works

Backfilling and Compaction at Building 1

 

Topping-Off Ceremony

 
 
January 13, 2009

Panoramic View of Building 1

Building 1 and 2 facing line, ready for Ground Floor Concreting

 

Rear Area of Building 2, concreted Ground Floor Level

Bird’s eye View of Building 2, 3rd floor formworks installation

 

View of Buildings 3, Slab-On-Grade preparatory works

Building 3 perforated pipe installation in preparation for Slab-On-Grade Concreting

 
December 17, 2008

Bird’s Eye View of Building 1

Bird's Eye View of Cyberpod Corinthian Project

 

Concreted 1st Lift of Retaining Wall, Building 3

Panoramic View of Building 1

 

View of Building 2 and 3 along Arcadia

 
 
December 10, 2008

Bird’s Eye View of Building 1

Excavation Works for Retaining wall, Building 3

 

Bird’s Eye View of Cyberpod Corinthian Project from Building 1

View of Building 2 & 3 along Arcadia

 
December 3, 2008

Bird’s Eye View of Building 1

Panoramic View of Building 1

 

Excavation Works for Retaining wall, Building 3

Bird’s Eye View of Cyberpod Corinthian Project from Building 1

 
November 21, 2008

Bird’s Eye View of Building 1

Panoramic View of Building 1

 

Footings Status along Arcadia
Building 2

 
 
November 12, 2008

Bird’s Eye View of Building 1

Panoramic View of Building 1

 

Concreted Footings along Arcadia, Building 2

 
 
November 6, 2008

Bird’s Eye View of Cyberpod
Corinthian Project Building 1

Panoramic View of Building 1

 

Concreted Suspended Slab at GLA1-B1/6A11A for G/F Level, Bldg 1

Rebar Works for Suspended Slab at GLB1-C1/6A11A for G/F Level, Bldg 1

 

Concreted Suspended Slab at GLA1-B1/1A6A, 2nd/F Level, Bldg 1

Concreted Suspended Slab at GLB1-C1/1A6A, 2nd/F Level, Bldg 1

 

Forms Stripping and Table Forms Removal at GL 1A6A/A1-A2, 2nd/F Level, Bldg 1

Forms Installation for Suspended Slab GL A1-B1/1A6A, 3rd/F Level, Bldg 1

 

Bulk Excavation at GL 1-12/A-B, Bldg 2 and 3

Concreted Footings at GL 5-8/A along Arcadia, Bldg 2

 

STP, Building 2

On-going Backfilling and Compaction at GL2-7/C-D, Bldg 2

 

On-going Backfilling, Gravel Bedding and Compaction at GL2-7/C-D, Bldg 2

Concreted 2nd Lift of Shear wall 1 at Bldg 3

 
October 30, 2008
 
 
October 15, 2008
 
 
 
September 10, 2008

Bird’s Eye View of Cyberpod
Corinthian Project

Installation of Safety Health and Environment Billboard

 

Exhaust Trench Excavation at
Building 1

Perforated Pipes Installation at
Building 1

 

Gravel Bedding at Combined Footings at GL 3A-4A/A2-B1, Building 1

Bird’s Eye View of Building 1

 

Forms Installation (2nd Lift) at Shear Walls – 1 and 4 (GL 3-6/B-C),
Building 2

STP Area Rebar Works, Building 2

 

Structural Excavations at Building 3

Bird’s Eye View of Building 3

 
July 8, 2008
 
 
July 1, 2008
 
 